NEW QUESTION 1
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
- A. Portfolio
- B. Project
- C. Program
- D. Operations
Answer: D
NEW QUESTION 2
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
- A. US$158,700
- B. US$172,500
- C. US$187,500
- D. US$245,600
Answer: C
NEW QUESTION 3
An input to the Plan Stakeholder Management process is:
- A. The project charter.
- B. The stakeholder analysis.
- C. A communication management plan.
- D. A stakeholder registe
Answer: D
NEW QUESTION 4
Every project creates a unique product, service, or result that may be:
- A. tangible
- B. targeted
- C. organized
- D. variable
Answer: A
NEW QUESTION 5
Which tools or techniques are used during the Close Project or Phase process?
- A. Reserve analysis and expert judgment
- B. Facilitation techniques and meetings
- C. Expert judgment and analytical techniques
- D. Performance reviews and meetings
Answer: C
NEW QUESTION 6
The following is a network diagram for a project.
The free float for Activity H is how many days?
- A. 4
- B. 5
- C. 10
- D. 11
Answer: A
NEW QUESTION 7
Which Project Time Management process includes bottom-up estimating as a tool or technique?
- A. Estimate Activity Resources
- B. Sequence Activities
- C. Estimate Activity Durations
- D. Develop Schedule
Answer: A
NEW QUESTION 8
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
- A. Analysis
- B. Appetite
- C. Tolerance
- D. Response
Answer: C
NEW QUESTION 9
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
- A. Business case
- B. Work breakdown structure
- C. Requirements documentation
- D. Risk register
Answer: C
NEW QUESTION 10
Which statement is true about the project management body of knowledge?
- A. Recognized by every project manager
- B. Constantly evolving
- C. The sum of all knowledge related to project management
- D. A sum of knowledge that should be applied on every project
Answer: B
NEW QUESTION 11
Which risk response strategy is common for both positive and negative risks?
- A. Share
- B. Accept
- C. Mitigate
- D. Transfer
Answer: B
NEW QUESTION 12
Which of the following Project Communication Management processes uses performance reports as an input?
- A. Manage Stakeholder Expectations
- B. Report Performance
- C. Distribute Information
- D. Plan Communications
Answer: C
NEW QUESTION 13
A temporary endeavor that creates a unique product or service is called a:
- A. Project
- B. Plan
- C. Program
- D. Portfolio
Answer: A
NEW QUESTION 14
What is project management?
- A. A logical grouping of project management inputs, outputs, tools, and techniques
- B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements
- C. Launching a process that can result in the authorization of a new project
- D. A formal, approved document that defines how the project is executed, monitored, and controlled
Answer: B
NEW QUESTION 15
Funding limit reconciliation is a tool and technique used in which process?
- A. Control Costs
- B. Determine Budget
- C. Estimate Costs
- D. Control Budget
Answer: B
NEW QUESTION 16
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
- A. Cost Plus Fixed Fee Contract (CPFF)
- B. Cost Plus Incentive Fee Contract (CPIF)
- C. Firm Fixed Price Contract (FFP)
- D. Fixed Price with Economic Price Adjustment Contract (FP-EPA)
Answer: A
NEW QUESTION 17
A key benefit of the Manage Communications process is that it enables:
- A. The best use of communication methods.
- B. An efficient and effective communication flow.
- C. Project costs to be reduced.
- D. The best use of communication technology.
Answer: B
NEW QUESTION 18
One of the tools and techniques of the Manage Project Team process is:
- A. organization charts.
- B. ground rules.
- C. organizational theory,
- D. conflict managemen
Answer: D
NEW QUESTION 19
An output of the Perform Integrated Change Control process is:
- A. Deliverables.
- B. Validated changes.
- C. The change log.
- D. The requirements traceability matri
Answer: C
NEW QUESTION 20
An input to the Estimate Activity Resources process is:
- A. Activity resource requirements.
- B. Published estimating data.
- C. Resource calendars.
- D. Resource breakdown structure (RBS).
Answer: C