NEW QUESTION 1
Project contracts generally fall into which of the following three broad categories?

  • A. Fixed-price, cost reimbursable, time and materials
  • B. Make-or-buy, margin analysis, fixed-price
  • C. Time and materials, fixed-price, margin analysis
  • D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

NEW QUESTION 2
The purpose of the Project Communications Management Knowledge Area is to:

  • A. Monitor and control communications throughout the entire project life cycle.
  • B. Maintain an optimal flow of information among all project participants.
  • C. Develop an appropriate approach for project communications.
  • D. Ensure timely and appropriate collection of project information.

Answer: D

NEW QUESTION 3
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be
involved in a project?

  • A. Feedback analysis
  • B. Stakeholder analysis
  • C. Communication management plan
  • D. Stakeholder management plan

Answer: D

NEW QUESTION 4
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

  • A. Utilize the change control process.
  • B. Crash the schedule to fix the defect.
  • C. Leave the defect in and work around it.
  • D. Fast-track the remaining developmen

Answer: A

NEW QUESTION 5
Which document includes the project scope, major deliverables, assumptions, and constraints?

  • A. Project charter
  • B. Project scope statement
  • C. Scope management plan
  • D. Project document updates

Answer: B

NEW QUESTION 6
The following chart contains information about the tasks in a project.
CAPM dumps exhibit
Based on the chart, what is the cost performance index (CPI) for Task 2? A. 0.8

  • A. 1
  • B. 1.25
  • C. 1.8

Answer: C

NEW QUESTION 7
A tool or technique in Perform Quality Control that a project manager would use is:

  • A. quality audits.
  • B. process analysis.
  • C. benchmarking.
  • D. inspection.

Answer: D

NEW QUESTION 8
Which grid shows which resources are tied to work packages?

  • A. Work breakdown structure (WBS)
  • B. Responsibility assignment matrix (RAM)
  • C. Project assignment chart
  • D. Personnel assignment matrix

Answer: B

NEW QUESTION 9
The Identify Stakeholders process is found in which Process Group?

  • A. Initiating
  • B. Monitoring and Controlling
  • C. Planning
  • D. Executing

Answer: A

NEW QUESTION 10
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

  • A. Plan Human Resource Management.
  • B. Acquire Project Team.
  • C. Manage Project Team.
  • D. Develop Project Tea

Answer: B

NEW QUESTION 11
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

  • A. Organizational standard processes
  • B. Marketplace conditions
  • C. Historical information
  • D. Templates

Answer: B

NEW QUESTION 12
Which process requires implementation of approved changes?

  • A. Direct and Manage Project Execution
  • B. Monitor and Control Project Work
  • C. Perform Integrated Change Control
  • D. Close Project or Phase

Answer: A

NEW QUESTION 13
"Tailoring" is defined as the:

  • A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
  • B. act of creating a project team with the specialized skills required to produce a required product or service.
  • C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
  • D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scop

Answer: A

NEW QUESTION 14
Which of the following is a group decision-making technique?

  • A. Brainstorming
  • B. Focus groups
  • C. Affinity diagram
  • D. Plurality

Answer: D

NEW QUESTION 15
Which enterprise environmental factors are considered during Estimate Costs?

  • A. Market conditions and published commercial information
  • B. Company structure and market conditions
  • C. Commercial information and company structure
  • D. Existing human resources and market conditions

Answer: A

NEW QUESTION 16
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

  • A. management
  • B. response
  • C. tolerance
  • D. appetite

Answer: D

NEW QUESTION 17
A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Answer: B

NEW QUESTION 18
Which of the following documents allows the project manager to assess risks that may require near term action?

  • A. Probability and impact matrix
  • B. Contingency analysis report
  • C. Risk urgency assessment
  • D. Rolling wave plan

Answer: C

NEW QUESTION 19
Which input provides suppliers with a clear set of goals, requirements, and outcomes?

  • A. Procurement statement of work
  • B. Purchase order
  • C. Source selection criteria
  • D. Bidder conference

Answer: A

NEW QUESTION 20
Enterprise environmental factors are an input to which process?

  • A. Control Scope
  • B. Define Scope
  • C. Plan Scope Management
  • D. Collect Requirements

Answer: C