for PMI certification, Real Success Guaranteed with Updated . 100% PASS CAPM Certified Associate in Project Management (PMI-100) exam Today!
Free CAPM Demo Online For Microsoft Certifitcation:
NEW QUESTION 1
Which of the following is an output of Define Scope?
- A. Project scope statement
- B. Project charter
- C. Project plan
- D. Project schedule
Answer: A
NEW QUESTION 2
An input to Close Project or Phase is:
- A. Accepted deliverables,
- B. Final products or services,
- C. Document updates,
- D. Work performance information.
Answer: A
NEW QUESTION 3
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
- A. Identify Risks
- B. Perform Qualitative Risk Analysis
- C. Plan Risk Management
- D. Perform Quantitative Risk Analysis
Answer: B
NEW QUESTION 4
The diagram below is an example of a:
- A. Risk breakdown structure (RBS).
- B. Project team.
- C. SWOT Analysis.
- D. Work breakdown structure (WBS).
Answer: A
NEW QUESTION 5
Which tool and technique is used in Conduct Procurements?
- A. Teaming agreements
- B. Expert judgment
- C. Bidder conferences
- D. Contract types
Answer: C
NEW QUESTION 6
The component of the risk management plan that documents how risk activities will be recorded is called:
- A. tracking
- B. scoping
- C. timing
- D. defining
Answer: A
NEW QUESTION 7
The project management processes presented in the PMBOK GuideĀ® should:
- A. always be applied uniformly.
- B. be selected as appropriate by the sponsor.
- C. be selected as appropriate by the project team.
- D. be applied based on ISO guideline
Answer: C
NEW QUESTION 8
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
- A. Plan Cost Management
- B. Plan Scope Management
- C. Plan Stakeholder Management
- D. Plan Schedule Management
Answer: C
NEW QUESTION 9
Which of the following tools and techniques is used in the Verify Scope process?
- A. Inspection
- B. Variance analysis
- C. Expert judgment
- D. Decomposition
Answer: A
NEW QUESTION 10
What is the number of stakeholders, if the project has 28 potential communication channels?
- A. 7
- B. 8
- C. 14
- D. 16
Answer: B
NEW QUESTION 11
Progressively elaborating high-level information into detailed plans is performed by the:
- A. project management office
- B. portfolio manager
- C. program manager
- D. project manager
Answer: D
NEW QUESTION 12
Which of the following is an input to the Perform Qualitative Risk Analysis process?
- A. Risk register
- B. Risk data quality assessment
- C. Risk categorization
- D. Risk urgency
Answer: A
NEW QUESTION 13
What is the total float of the critical path?
- A. Can be any number
- B. Zero or positive
- C. Zero or negative
- D. Depends on the calendar
Answer: C
NEW QUESTION 14
Resource calendars are included in the:
- A. staffing management plan.
- B. work breakdown structure (WBS).
- C. project communications plan.
- D. project charte
Answer: A
NEW QUESTION 15
Lessons learned are created and project resources are released in which Process Group?
- A. Planning
- B. Executing
- C. Closing
- D. Initiating
Answer: C
NEW QUESTION 16
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
- A. Project document updates
- B. Activity list
- C. Activity attributes
- D. Project calendars
Answer: C
NEW QUESTION 17
Which of the following includes how requirements activities will be planned, tracked, and reported?
- A. Configuration management plan
- B. Scope baseline
- C. Requirements management plan
- D. Schedule baseline
Answer: C
NEW QUESTION 18
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
- A. Plan Procurement Management
- B. Control Procurements
- C. Collect Requirements
- D. Plan Cost Management
Answer: A
NEW QUESTION 19
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
- A. Compromising
- B. Collaborating
- C. Smoothing
- D. Problem Solving
Answer: C
NEW QUESTION 20
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
- A. Close Procurements.
- B. Control Procurements.
- C. Plan Procurements.
- D. Conduct Procurement
Answer: D
Recommend!! Get the Full CAPM dumps in VCE and PDF From Certshared, Welcome to Download: https://www.certshared.com/exam/CAPM/ (New 704 Q&As Version)