NEW QUESTION 1
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
- A. Limited
- B. Low to moderate
- C. Moderate to high
- D. High to almost total
Answer: C
NEW QUESTION 2
An output of the Develop Project Team process is:
- A. change requests
- B. team performance assessments
- C. project staff assignments
- D. project documents updates
Answer: B
NEW QUESTION 3
The precedence diagramming method (PDM) is also known as:
- A. Arrow Diagram.
- B. Critical Path Methodology (CPM).
- C. Activity-On-Node (AON).
- D. schedule network diagra
Answer: C
NEW QUESTION 4
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
- A. Control charts
- B. Pareto diagrams
- C. Ishikavva diagrams
- D. Checksheets
Answer: D
NEW QUESTION 5
Which stakeholder approves a project's result?
- A. Customer
- B. Sponsor
- C. Seller
- D. Functional manager
Answer: A
NEW QUESTION 6
Which of the following tools or techniques is used for Estimate Activity Durations?
- A. Critical path method
- B. Rolling wave planning
- C. Precedence diagramming method
- D. Parametric estimating
Answer: D
NEW QUESTION 7
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
- A. Result
- B. Product
- C. Service
- D. Improvement
Answer: A
NEW QUESTION 8
The scope management plan and scope baseline are contained in:
- A. organizational process assets
- B. a requirements traceability matrix
- C. the project charter
- D. the project management plan
Answer: D
NEW QUESTION 9
Which of the following is a tool or technique used in the Acquire Project Team process?
- A. Networking
- B. Training
- C. Negotiation
- D. Issue log
Answer: C
NEW QUESTION 10
The zero duration of milestones in project planning occurs because milestones:
- A. Are unpredictable and challenge the Plan Schedule Management process.
- B. Occur at random times in the project plans.
- C. Represent a moment in time such as a significant project point or event.
- D. Represent both significant and insignificant points in the project and are difficult to anticipat
Answer: C
NEW QUESTION 11
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
- A. Project
- B. Functional
- C. Program
- D. Portfolio
Answer: D
NEW QUESTION 12
Which tool or technique is used in the Perform Integrated Change Control process?
- A. Decomposition
- B. Modeling techniques
- C. Resource optimization
- D. Meetings
Answer: D
NEW QUESTION 13
Cost baseline is an output of which of the following processes?
- A. Control Costs
- B. Determine Budget
- C. Estimate Costs
- D. Estimate Activity Resources
Answer: B
NEW QUESTION 14
An example of a group decision-ma king technique is:
- A. Nominal group technique.
- B. Majority.
- C. Affinity diagram.
- D. Multi-criteria decision analysi
Answer: B
NEW QUESTION 15
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
- A. Only once, at the beginning
- B. At the beginning and the end
- C. Once during each phase
- D. Repeatedly
Answer: D
NEW QUESTION 16
Exhibit A is an example of which of the following types of Sequence Activities?
- A. Activity-on-arrow diagramming
- B. Precedence diagramming
- C. Project schedule network diagramming
- D. Mathematical analysis diagramming
Answer: B
NEW QUESTION 17
Which tool or technique is used in the Develop Project Management Plan process?
- A. Pareto diagram
- B. Performance reporting
- C. SWOT analysis
- D. Expert judgment
Answer: D
NEW QUESTION 18
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
- A. Cost Plus Incentive Fee (CPIF)
- B. Fixed Price Incentive Fee (FPIF)
- C. Cost Pius Award Re (CPAF)
- D. Time and Material (T&M)
Answer: B
NEW QUESTION 19
The product scope description is used to:
- A. Gain stakeholders' support for the project.
- B. Progressively elaborate the characteristics of the product, service, or result.
- C. Describe the project in great detail.
- D. Define the process and criteria for accepting a completed product, service, or resul
Answer: B
NEW QUESTION 20
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
- A. Reserve analysis
- B. Three-point estimating
- C. Parametric estimating
- D. Analogous estimating
Answer: D