NEW QUESTION 1
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
- A. budget at completion (BAC)
- B. earned value management (EVM)
- C. to-complete performance index
- D. cost performance index
Answer: C
NEW QUESTION 2
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
- A. project documents updates.
- B. project management plan updates.
- C. change requests.
- D. work performance informatio
Answer: D
NEW QUESTION 3
The project has a current cost performance index of 0.80. Assuming this performance wi
continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
- A. $800
- B. $1000
- C. $1250
- D. $1800
Answer: A
NEW QUESTION 4
The project scope statement and resource calendars are inputs to which Project Time Management process?
- A. Sequence Activities
- B. Estimate Activity Resources
- C. Develop Schedule
- D. Control Schedule
Answer: C
NEW QUESTION 5
Which of the following is an input to Direct and Manage Project Execution?
- A. Performance reports
- B. Project charter
- C. Outputs from planning processes
- D. Enterprise environmental factors
Answer: D
NEW QUESTION 6
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
- A. Executing.
- B. Initiating,
- C. Monitoring and Controlling.
- D. Plannin
Answer: C
NEW QUESTION 7
Which of the following response strategies are appropriate for negative risks or threats?
- A. Share, Accept, Transfer, or Mitigate
- B. Exploit, Enhance, Share, or Accept
- C. Mitigate, Share, Avoid, or Accept
- D. Avoid, Mitigate, Transfer, or Accept
Answer: D
NEW QUESTION 8
An input to the Create WBS process is a:
- A. project charter.
- B. stakeholder register.
- C. project scope statement.
- D. requirements traceability matri
Answer: C
NEW QUESTION 9
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
- A. Project Communications Management
- B. Project Integration Management
- C. Project Risk Management
- D. Project Scope Management
Answer: B
NEW QUESTION 10
The scope management plan and scope baseline are contained in:
- A. organizational process assets
- B. a requirements traceability matrix
- C. the project charter
- D. the project management plan
Answer: D
NEW QUESTION 11
A tool and technique used during the Perform Qualitative Risk Analysis process is:
- A. risk data quality assessment.
- B. variance and trend analysis.
- C. data gathering and representation techniques.
- D. risk audit
Answer: A
NEW QUESTION 12
A project charter is an output of which Process Group?
- A. Executing
- B. Planning
- C. Initiating
- D. Closing
Answer: C
NEW QUESTION 13
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
- A. Project Time Management
- B. Project Cost Management
- C. Project Scope Management
- D. Project Human Resource Management
Answer: A
NEW QUESTION 14
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
- A. Information management systems
- B. Work performance reports
- C. Stakeholder analysis
- D. Data gathering and representation
Answer: A
NEW QUESTION 15
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
- A. Failure modes and effects analysis
- B. Design of experiments
- C. Quality checklist
- D. Risk analysis
Answer: B
NEW QUESTION 16
Inputs to the Plan Risk Management process include the:
- A. cost management plan.
- B. risk management plan,
- C. activity list,
- D. risk registe
Answer: A
NEW QUESTION 17
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
- A. Earned value management.
- B. Enterprise environmental factors.
- C. Organizational process assets.
- D. Work performance informatio
Answer: D
NEW QUESTION 18
An input required in Define Scope is an organizational:
- A. structure.
- B. process asset.
- C. matrix.
- D. breakdown structur
Answer: B
NEW QUESTION 19
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
- A. Develop Project Team.
- B. Manage Project Team.
- C. Acquire Project Team.
- D. Plan Human Resource Managemen
Answer: D
NEW QUESTION 20
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
- A. Work performance reports
- B. Assumptions logs
- C. Network diagrams
- D. Academic studies
Answer: D