for PMI certification, Real Success Guaranteed with Updated . 100% PASS CAPM Certified Associate in Project Management (PMI-100) exam Today!

Check CAPM free dumps before getting the full version:

NEW QUESTION 1
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

  • A. budget at completion (BAC)
  • B. earned value management (EVM)
  • C. to-complete performance index
  • D. cost performance index

Answer: C

NEW QUESTION 2
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

  • A. project documents updates.
  • B. project management plan updates.
  • C. change requests.
  • D. work performance informatio

Answer: D

NEW QUESTION 3
The project has a current cost performance index of 0.80. Assuming this performance wi
continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

  • A. $800
  • B. $1000
  • C. $1250
  • D. $1800

Answer: A

NEW QUESTION 4
The project scope statement and resource calendars are inputs to which Project Time Management process?

  • A. Sequence Activities
  • B. Estimate Activity Resources
  • C. Develop Schedule
  • D. Control Schedule

Answer: C

NEW QUESTION 5
Which of the following is an input to Direct and Manage Project Execution?

  • A. Performance reports
  • B. Project charter
  • C. Outputs from planning processes
  • D. Enterprise environmental factors

Answer: D

NEW QUESTION 6
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

  • A. Executing.
  • B. Initiating,
  • C. Monitoring and Controlling.
  • D. Plannin

Answer: C

NEW QUESTION 7
Which of the following response strategies are appropriate for negative risks or threats?

  • A. Share, Accept, Transfer, or Mitigate
  • B. Exploit, Enhance, Share, or Accept
  • C. Mitigate, Share, Avoid, or Accept
  • D. Avoid, Mitigate, Transfer, or Accept

Answer: D

NEW QUESTION 8
An input to the Create WBS process is a:

  • A. project charter.
  • B. stakeholder register.
  • C. project scope statement.
  • D. requirements traceability matri

Answer: C

NEW QUESTION 9
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  • A. Project Communications Management
  • B. Project Integration Management
  • C. Project Risk Management
  • D. Project Scope Management

Answer: B

NEW QUESTION 10
The scope management plan and scope baseline are contained in:

  • A. organizational process assets
  • B. a requirements traceability matrix
  • C. the project charter
  • D. the project management plan

Answer: D

NEW QUESTION 11
A tool and technique used during the Perform Qualitative Risk Analysis process is:

  • A. risk data quality assessment.
  • B. variance and trend analysis.
  • C. data gathering and representation techniques.
  • D. risk audit

Answer: A

NEW QUESTION 12
A project charter is an output of which Process Group?

  • A. Executing
  • B. Planning
  • C. Initiating
  • D. Closing

Answer: C

NEW QUESTION 13
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

  • A. Project Time Management
  • B. Project Cost Management
  • C. Project Scope Management
  • D. Project Human Resource Management

Answer: A

NEW QUESTION 14
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

  • A. Information management systems
  • B. Work performance reports
  • C. Stakeholder analysis
  • D. Data gathering and representation

Answer: A

NEW QUESTION 15
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

  • A. Failure modes and effects analysis
  • B. Design of experiments
  • C. Quality checklist
  • D. Risk analysis

Answer: B

NEW QUESTION 16
Inputs to the Plan Risk Management process include the:

  • A. cost management plan.
  • B. risk management plan,
  • C. activity list,
  • D. risk registe

Answer: A

NEW QUESTION 17
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

  • A. Earned value management.
  • B. Enterprise environmental factors.
  • C. Organizational process assets.
  • D. Work performance informatio

Answer: D

NEW QUESTION 18
An input required in Define Scope is an organizational:

  • A. structure.
  • B. process asset.
  • C. matrix.
  • D. breakdown structur

Answer: B

NEW QUESTION 19
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

  • A. Develop Project Team.
  • B. Manage Project Team.
  • C. Acquire Project Team.
  • D. Plan Human Resource Managemen

Answer: D

NEW QUESTION 20
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

  • A. Work performance reports
  • B. Assumptions logs
  • C. Network diagrams
  • D. Academic studies

Answer: D

P.S. Certleader now are offering 100% pass ensure CAPM dumps! All CAPM exam questions have been updated with correct answers: https://www.certleader.com/CAPM-dumps.html (704 New Questions)