Q111. - (Topic 2) 

A project has lost critical project team members. Which of the following scheduling methods would be used to analyze the impact of this resource constraint? 

A. CCM 

B. PDM 

C. ADM 

D. CCB 

Answer:


Q112. - (Topic 3) 

A project manager would like to develop a graphical representation of the issues being encountered during a software development project. Which of the following will assist the team by showing the MOST important issues? 

A. PERT diagram 

B. Fishbone diagram 

C. Run chart 

D. Pareto chart 

Answer:


Q113. - (Topic 1) 

A project is experiencing quality issues with the deliverable product. Which of the following tools would be used to identify and prioritize the MOST commonly occurring issues? 

A. Scatter diagram 

B. Pareto chart 

C. Ishikawa diagram 

D. Trend analysis 

Answer:


Q114. - (Topic 2) 

When working on the monitoring and controlling phase of the project lifecycle, which of the following activities would occur? 

A. Third-party auditors will evaluate documentation. 

B. Team members will participate in lessons learned events. 

C. Project manager will direct and manage work tasks. 

D. Senior management will review the project scope document. 

Answer:


Q115. - (Topic 2) 

A project manager is meeting with the key stakeholders to understand the problem, gather business requirements, and identify project objectives. Which of the following allows this information to be formally documented and allows the project manager to measure success? 

A. Project management plan 

B. Project charter 

C. Request for proposal 

D. Statement of work 

Answer:


Q116. - (Topic 3) 

A project manager receives notice that a new law will soon go into effect that may impact a current project. After confirming the information, which of the following should the project manager update FIRST? 

A. Stakeholder register 

B. Risk register 

C. Issue log 

D. Qualitative data 

Answer:


Q117. - (Topic 2) 

A project manager wants to ensure that end users receive proper training prior to implementation. In which of the following documents should the project manager outline the necessary training? 

A. Work breakdown structure 

B. Transition plan 

C. Communication plan 

D. Lessons learned 

Answer:


Q118. - (Topic 1) 

In month nine of a 12-month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more accurate assessment, the project manager calculates the Cost Variance (CV) using which of the following formulas? 

A. CV = PV – AC 

B. CV = AC – EV 

C. CV = EV – PV 

D. CV = EV – AC 

Answer:


Q119. - (Topic 2) 

While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case. Which of the following types of schedule methods will reflect this? 

A. PERT 

B. CPM 

C. CCM 

D. GERT 

Answer:


Q120. - (Topic 3) 

When an issue is considered trivial and not worth the time or effort necessary to resolve it, which of the following is the BEST conflict resolution technique? 

A. Negotiating 

B. Smoothing 

C. Compromising 

D. Avoiding 

Answer: