It is impossible to pass PMP PMP exam without any help in the short term. Come to us soon and find the most advanced, correct and guaranteed . You will get a surprising result by our .
PMP PMP Free Dumps Questions Online, Read and Test Now.
NEW QUESTION 1
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
- A. Timing
- B. Methodology
- C. Risk categories
- D. Budgeting
Answer: A
NEW QUESTION 2
Which of the following response strategies are appropriate for negative risks or threats?
- A. Share, Accept, Transfer, or Mitigate
- B. Exploit, Enhance, Share, or Accept
- C. Mitigate, Share, Avoid, or Accept
- D. Avoid, Mitigate, Transfer, or Accept
Answer: D
NEW QUESTION 3
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?
- A. Risk analysis
- B. Risk tolerance
- C. Risk management
- D. Risk attitude
Answer: B
NEW QUESTION 4
Which activity may occur at project or phase closure?
- A. Acceptance of deliverables
- B. Change requests
- C. Project management plan updates
- D. Benchmarking
Answer: A
NEW QUESTION 5
In an organization with a projectized organizational structure, who controls the project budget?
- A. Functional manager
- B. Project manager
- C. Program manager
- D. Project management office
Answer: B
NEW QUESTION 6
Which of the following is a means of reaching a group decision in which everyone agrees on a single course of action?
- A. Dictatorship
- B. Majority
- C. Plurality
- D. Unanimity
Answer: D
NEW QUESTION 7
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
- A. Start-to-start (SS).
- B. Start-to-finish (SF).
- C. Finish-to-start (FS).
- D. Finish-to-finish (FF).
Answer: C
Explanation: Topic 5, Closing
NEW QUESTION 8
Which statement correctly describes the value of a business case?
- A. It provides the necessary information to determine if a project is worth the required investment.
- B. It provides for alternative dispute resolution procedures in event of contract default.
- C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
- D. It is used to help a project manager understand the scope of commercial advantages.
Answer: A
NEW QUESTION 9
An example of a group decision-making technique is:
- A. nominal group technique
- B. majority
- C. affinity diagram
- D. multi-criteria decision analysis
Answer: A
NEW QUESTION 10
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
- A. Cost Plus Award Fee Contract (CPAF)
- B. Firm-Fixed -Price Contract (FFP)
- C. Time and Material Contract (T&M)
- D. Cost Plus Incentive Fee Contract (CPIF)
Answer: C
NEW QUESTION 11
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
- A. Control Quality
- B. Monitor and Control Project Work
- C. Control Scope
- D. Perform Integrated Change Control
Answer: D
NEW QUESTION 12
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
- A. Schedule
- B. Quality
- C. Communications
- D. Cost
Answer: C
NEW QUESTION 13
Which characteristic is unique to project work and does not apply to operational work?
- A. Performed by individuals
- B. Limited by constraints
- C. Temporary
- D. Performed to achieve organizational objectives
Answer: C
NEW QUESTION 14
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
- A. Scope audits
- B. Scope reviews
- C. Quality audits
- D. Control chart
Answer: C
NEW QUESTION 15
Which process numerically analyzes the effect of identified risks on overall project objectives?
- A. Plan Risk Management
- B. Plan Risk Responses
- C. Perform Quantitative Risk Analysis
- D. Perform Qualitative Risk Analysis
Answer: C
NEW QUESTION 16
Cost variance (CV) is equal to earned value:
- A. Minus actual cost [EV - AC].
- B. Minus planned value [EV - PV].
- C. Divided by actual cost [EV/AC].
- D. Divided by planned value [EV/PV].
Answer: A
100% Valid and Newest Version PMP Questions & Answers shared by Surepassexam, Get Full Dumps HERE: https://www.surepassexam.com/PMP-exam-dumps.html (New 918 Q&As)