Want to know Passleader PMP Exam practice test features? Want to lear more about PMP Project Management Professional certification experience? Study Actual PMP PMP answers to Renewal PMP questions at Passleader. Gat a success with an absolute guarantee to pass PMP PMP (Project Management Professional) test on your first attempt.

PMP PMP Free Dumps Questions Online, Read and Test Now.

NEW QUESTION 1

Which process should be conducted from the project inception through completion?

  • A. Monitor and Control Project Work
  • B. Perform Quality Control
  • C. Perform Integrated Change Control
  • D. Monitor and Control Risks

Answer: C

NEW QUESTION 2

The correct equation for schedule variance (SV) is earned value:

  • A. minus planned value [EV - PV].
  • B. minus actual cost [EV - AC].
  • C. divided by planned value [EV/PV],
  • D. divided by actual cost [EV/AC].

Answer: A

NEW QUESTION 3

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating

Answer: C

NEW QUESTION 4

Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?

  • A. Estimate Activity Durations
  • B. Sequence Activities
  • C. Define Activities
  • D. Activity Attributes

Answer: C

NEW QUESTION 5

Which process occurs within the Monitoring and Controlling Process Group?

  • A. Control Costs
  • B. Plan Quality
  • C. Perform Quantitative Risk Analysis
  • D. Determine Budget

Answer: A

NEW QUESTION 6

Which piece of information is part of the WBS Dictionary?

  • A. Responsible organization
  • B. Change requests
  • C. Validated deliverables
  • D. Organizational process assets

Answer: A

NEW QUESTION 7

Which of the following is an output of the Conduct Procurements process?

  • A. Project statement of work
  • B. Selected sellers
  • C. Risk register updates
  • D. Teaming agreements

Answer: B

NEW QUESTION 8

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  • A. Collect Requirements
  • B. Plan Scope Management
  • C. Define Scope
  • D. Define Activities

Answer: A

NEW QUESTION 9

The project scope statement and resource calendars are inputs to which Project Time Management process?

  • A. Sequence Activities
  • B. Estimate Activity Resources
  • C. Develop Schedule
  • D. Control Schedule

Answer: C

NEW QUESTION 10

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

  • A. Interrelationship digraphs
  • B. Tree diagram
  • C. Affinity diagram
  • D. Network diagram

Answer: B

NEW QUESTION 11

Which of the following are inputs to Activity Definition?

  • A. Project Scope Statement and Work Breakdown Structure
  • B. Activity list and Arrow Diagram
  • C. Change Requests Lists and Organizational Process Assets
  • D. Project Management Plan and Resource Availability

Answer: A

NEW QUESTION 12

The Verify Scope process is primarily concerned with:

  • A. formalizing acceptance of the completed project deliverables.
  • B. accuracy of the work deliverables.
  • C. formalizing approval of the scope statement.
  • D. accuracy of the work breakdown structure (WBS).

Answer: A

NEW QUESTION 13

An input required to develop a preliminary project scope statement is:

  • A. Organizational Structure
  • B. Organizational Process Assets
  • C. Organizational Matrix
  • D. Organizational Breakdown Structures

Answer: B

NEW QUESTION 14

Which of the following is an input to Control Scope?

  • A. Project schedule
  • B. Organizational process assets updates
  • C. Project document updates
  • D. Work performance information

Answer: B

NEW QUESTION 15

Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face?

  • A. Co-location team
  • B. Virtual team
  • C. Departmental team
  • D. Consultant team

Answer: B

NEW QUESTION 16

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

  • A. Perform Quality Control
  • B. Quality Policy
  • C. Perform Quality Assurance
  • D. Quality Planning

Answer: C

NEW QUESTION 17

A tool and technique used during the Create WBS process is:

  • A. decomposition
  • B. expert judgment
  • C. inspection
  • D. variance analysis

Answer: A

NEW QUESTION 18

Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?

  • A. Control accounts
  • B. Milestones
  • C. Management points
  • D. Measurement points

Answer: A

NEW QUESTION 19

Which of the following is TRUE about most project life cycles?

  • A. Staffing level is highest at the start.
  • B. The stakeholders' influence is highest at the start.
  • C. The level of uncertainty is lowest at the start.
  • D. The cost of changes is highest at the start.

Answer: B

NEW QUESTION 20

Stakeholder satisfaction should be managed as a key project:

  • A. Benefit
  • B. Initiative
  • C. Objective
  • D. Process

Answer: C

NEW QUESTION 21

Which type of analysis is used to develop the communications management plan?

  • A. Product
  • B. Cost benefit
  • C. Stakeholder
  • D. Research

Answer: C

NEW QUESTION 22

The zero duration of milestones in project planning occurs because milestones:

  • A. Are unpredictable and challenge the Plan Schedule Management process.
  • B. Occur at random times in the project plans.
  • C. Represent a moment in time such as a significant project point or event.
  • D. Represent both significant and insignificant points in the project and are difficult to anticipate.

Answer: C

NEW QUESTION 23

Which type of dependency is contractually required or inherent in the nature of the work?

  • A. External
  • B. Lead
  • C. Discretionary
  • D. Mandatory

Answer: D

NEW QUESTION 24

The Define Scope process is in which of the following Process Groups?

  • A. Initiating
  • B. Planning
  • C. Monitoring and Controlling
  • D. Executing

Answer: B

NEW QUESTION 25

Which is an output of the Collect Requirements process?

  • A. Requirements traceability matrix
  • B. Project scope statement
  • C. WBS dictionary
  • D. Work performance measurements

Answer: A

NEW QUESTION 26
......

Recommend!! Get the Full PMP dumps in VCE and PDF From DumpSolutions.com, Welcome to Download: https://www.dumpsolutions.com/PMP-dumps/ (New 918 Q&As Version)