NEW QUESTION 1
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
- A. Planning.
- B. Executing,
- C. Monitoring and Controlling.
- D. Closing.
Answer: A
NEW QUESTION 2
The staffing management plan is part of the:
- A. organizational process assets.
- B. resource calendar.
- C. human resource plan.
- D. Develop Project Team process.
Answer: C
NEW QUESTION 3
Which illustrates the connection between work that needs to be done and its project team members?
- A. Work breakdown structure
- B. Network diagrams
- C. Staffing management plan
- D. Responsibility matrix
Answer: D
NEW QUESTION 4
Risk categorization is a tool or technique used in which process?
- A. Plan Risk Responses
- B. Plan Risk Management
- C. Perform Qualitative Risk Analysis
- D. Perform Quantitative Risk Analysis
Answer: C
NEW QUESTION 5
Which of the following characteristics are found in a functional organizational structure?
- A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget
- B. Limited project manager authority, limited resource availability, and a part-time project manager's role
- C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role
- D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff
Answer: A
NEW QUESTION 6
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
- A. Brainstorming
- B. Strategies for opportunities
- C. Decision tree analysis
- D. Risk data quality assessment
Answer: C
NEW QUESTION 7
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
- A. Estimate at completion
- B. Cost performance
- C. Schedule performance
- D. To-complete performance
Answer: D
NEW QUESTION 8
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
- A. Supportive
- B. Leading
- C. Neutral
- D. Resistant
Answer: B
NEW QUESTION 9
What is the number of stakeholders, if the project has 28 potential communication channels?
- A. 7
- B. 8
- C. 14
- D. 16
Answer: B
NEW QUESTION 10
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
- A. Direct
- B. Interactive
- C. Pull
- D. Push
Answer: D
NEW QUESTION 11
Which is a tool or technique used in Define Scope?
- A. Templates, forms, and standards
- B. Change requests
- C. Product analysis
- D. Project assumptions
Answer: C
NEW QUESTION 12
Which process in Project Time Management includes reserve analysis as a tool or technique?
- A. Estimate Activity Resources
- B. Sequence Activities
- C. Estimate Activity Durations
- D. Develop Schedule
Answer: C
NEW QUESTION 13
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
- A. Risk identification
- B. Qualitative risk analysis
- C. Risk management planning
- D. Quantitative risk analysis
Answer: B
NEW QUESTION 14
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
- A. scope creep.
- B. a change request.
- C. work performance information.
- D. deliverables.
Answer: A
NEW QUESTION 15
Which characteristic do projects and operational work share in common?
- A. Performed by systems
- B. Constrained by limited resources
- C. Repetitiveness
- D. Uniqueness
Answer: B
NEW QUESTION 16
Which provides the basic framework for managing a project?
- A. Project life cycle
- B. Work breakdown structure (WBS)
- C. Enterprise environmental factors
- D. Project initiation
Answer: A