NEW QUESTION 1
Which process determines the risks that may affect the project and documents their characteristics?

  • A. Control Risks
  • B. Plan Risk Management
  • C. Plan Risk Responses
  • D. Identify Risks

Answer: D

NEW QUESTION 2
Which of the following is a project constraint?

  • A. Twenty-five percent staff turnover is expected.
  • B. The technology to be used is cutting-edge.
  • C. Project leadership may change due to volatile political environment.
  • D. The product is needed in 250 days.

Answer: D

NEW QUESTION 3
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

  • A. Authority
  • B. Role
  • C. Competency
  • D. Responsibility

Answer: C

NEW QUESTION 4
Within project integration management, the statement of work (SOW) references which aspects of the project?

  • A. Strategic plan, business need, and product scope description
  • B. Contract, enterprise environmental factors, and organizational process assets
  • C. Business plan, project management plan, and project schedule
  • D. Product lifecycle, business objective, and management strategy

Answer: A

NEW QUESTION 5
Which of the following is an input to the Develop Project Charter process?

  • A. Work performance information
  • B. Project management plan
  • C. Business case
  • D. Change requests

Answer: C

NEW QUESTION 6
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

  • A. Cost-reimbursable
  • B. Time and material
  • C. Fixed price or lump-sum
  • D. Cost-plus-fixed-fee

Answer: C

NEW QUESTION 7
What is the function of a Project Management Office (PMO)?

  • A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.
  • B. To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.
  • C. To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.
  • D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Answer: A

NEW QUESTION 8
Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?

  • A. Earned value analysis
  • B. Trend analysis
  • C. Project records
  • D. Performance reviews

Answer: C

NEW QUESTION 9
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

  • A. Executing.
  • B. Initiating,
  • C. Monitoring and Controlling.
  • D. Planning.

Answer: C

NEW QUESTION 10
The Human Resource Management processes are:

  • A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
  • B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
  • C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
  • D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Answer: A

NEW QUESTION 11
The following is a network diagram for a project.
PMP dumps exhibit
The free float for Activity E is how many days?

  • A. 2
  • B. 3
  • C. 5
  • D. 8

Answer: C

NEW QUESTION 12
Which characteristics do effective project managers possess?

  • A. Project management knowledge, performance skills, and personal effectiveness
  • B. Preparedness, project management knowledge, and personality characteristics
  • C. General management, preparedness, and project management knowledge
  • D. Assertiveness, collaboration, and performance skills

Answer: A

NEW QUESTION 13
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

  • A. Applying calendars
  • B. Resource leveling
  • C. Resource planning
  • D. Resource conflict management

Answer: B

NEW QUESTION 14
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

  • A. Continuous
  • B. Discrete
  • C. Regulated
  • D. Arbitrary

Answer: A

NEW QUESTION 15
Which technique is utilized in the Control Schedule process?

  • A. Performance measure
  • B. Baseline schedule
  • C. Schedule network analysis
  • D. Variance analysis

Answer: D

NEW QUESTION 16
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

  • A. Estimate Costs
  • B. Estimate Activity Resources
  • C. Control Costs
  • D. Determine Budget

Answer: B

100% Valid and Newest Version PMP Questions & Answers shared by Surepassexam, Get Full Dumps HERE: https://www.surepassexam.com/PMP-exam-dumps.html (New 918 Q&As)