Actualtests offers free demo for PRINCE2-Foundation exam. "PRINCE2 Foundation exam", also known as PRINCE2-Foundation exam, is a PRINCE2-Exams Certification. This set of posts, Passing the PRINCE2-Exams PRINCE2-Foundation exam, will help you answer those questions. The PRINCE2-Foundation Questions & Answers covers all the knowledge points of the real exam. 100% real PRINCE2-Exams PRINCE2-Foundation exams and revised by experts!

Free demo questions for PRINCE2-Exams PRINCE2-Foundation Exam Dumps Below:

NEW QUESTION 1

Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Plan
  • C. CommunicationManagement Strategy
  • D. Project Product Description

Answer: A

NEW QUESTION 2

Which of the following is NOT a purpose of the Closing a Project process?

  • A. Plan the activities required to close a project
  • B. Enable a comparison of the original objectives of a project against what was actually achieved
  • C. Enable premature closureif the Project Board request that a project should no longer continue
  • D. Provide a fixed point at which acceptance for the project product is confirmed

Answer: A

NEW QUESTION 3

When considering risks, which describes an opportunity in a project?

  • A. An uncertain event that couldhave a negative impact on objectives
  • B. An uncertain event that could have a favourable impact on objectives
  • C. An event that has occurred resulting in a negative impact on objectives
  • D. An event that has occurred resulting in a favourable impact on objectives

Answer: B

NEW QUESTION 4

Which statement about the Directing a Project process is true?

  • A. Provides a mechanism for the Project Board to assure that there is continuedbusiness justification
  • B. Covers the day-to-day activities of the Project Manager
  • C. Ensures there are regular progress meetings
  • D. Begins on completion of the Initiating a Project process

Answer: A

NEW QUESTION 5

Which role is part of the project management team?

  • A. Change Authority
  • B. Quality assurance
  • C. Stakeholder
  • D. Corporate or programme management

Answer: A

NEW QUESTION 6

Which describes the 'Implement' step within the recommended risk management procedure?

  • A. Project Support will allocate the risk budget to fund the selected risk responses
  • B. The risk owner will decide the best response to control the risk
  • C. The risk owner and the risk actionee will carry out activities to control and deal with the risk
  • D. The Project Manager will formulate the RiskManagement Strategy

Answer: C

NEW QUESTION 7

Which is a purpose of a Lessons Log?

  • A. Note any lessons that are raised in Checkpoint Reports
  • B. Record that corrective action is being taken
  • C. Escalate lessons to the Project Board
  • D. Raise improvements with Project Assurance

Answer: A

NEW QUESTION 8

Why does PRINCE2 recommend three different levels of plans?

  • A. To cover initiation, specialist work and exception situations
  • B. To provide appropriate detailto each of the different levels of management within the project
  • C. As an allowance for initiation, product delivery and project closure
  • D. To match the different aspects of the product-based planning technique

Answer: B

NEW QUESTION 9

Which is a purpose of the Closing a Project process?

  • A. Authorize the final stage of the project
  • B. Confirm that all benefits defined in the Business Casehave been achieved
  • C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
  • D. Delegate day-to-day management of the end of the project to the Project Manager

Answer: C

NEW QUESTION 10

Which is a purpose of a Lessons Report?

  • A. Improve the project management method for future projects
  • B. Detail open issues and risks that need to be managed after the project has closed
  • C. Compare the actual performance of the final stage against its plan
  • D. Provide a summary of the benefits realized during the project

Answer: A

NEW QUESTION 11

Which is the purpose of the Change theme?

  • A. Prevent change to baselined products
  • B. Identify, assess and control any potential and approved changes to baselined products
  • C. Establish mechanisms to monitor and compare actual achievements against those planned
  • D. Assess and control uncertainty

Answer: B

NEW QUESTION 12

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  • A. Change
  • B. Cross-functional
  • C. Unique
  • D. Risk

Answer: B

NEW QUESTION 13

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

  • A. quality
  • B. supplier
  • C. risk
  • D. product

Answer: B

NEW QUESTION 14

Which is a purpose of the Project Product Description?

  • A. Define the key responsibilities for delivering product quality
  • B. Provide information about the state of products
  • C. Define the quality anticipated by the customer
  • D. Provide product cost input tothe Business Case

Answer: C

NEW QUESTION 15

Which is NOT a true statement about the Managing a Stage Boundary process?

  • A. It providessufficient information for the Project Board to review the success of the current stage
  • B. It is used to create an Exception Plan if requested by the Project Board
  • C. It provides a fixed point at which acceptance of the project product is confirmed
  • D. It is executed at, or close to, the end of each management stage, except the final one

Answer: C

NEW QUESTION 16

Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

  • A. Business Case
  • B. Plans
  • C. Progress
  • D. Quality

Answer: C

NEW QUESTION 17

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

  • A. a corporate
  • B. a temporary
  • C. an external
  • D. a technical

Answer: B

NEW QUESTION 18

Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

  • A. Project Assurance
  • B. Project Support
  • C. the risk actionee
  • D. the risk owner

Answer: C

NEW QUESTION 19

Which enables the project's products and all interdependencies to be clearly identified and documented?

  • A. Product breakdown structure
  • B. Quality Management Strategy
  • C. Product-based planning technique
  • D. Quality review technique

Answer: C

NEW QUESTION 20

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Progress
  • B. Change
  • C. Organization
  • D. Quality

Answer: A

NEW QUESTION 21

In what process is the authorization to deliver the project's products given?

  • A. Starting up a Project
  • B. Initiating a Project
  • C. Managing a Stage Boundary
  • D. Directing a Project

Answer: D

NEW QUESTION 22

Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Stage Plan
  • B. Communication Management Strategy
  • C. Follow-on action recommendations
  • D. Quality Management Strategy

Answer: B

NEW QUESTION 23

Which is an objective of the Managing Product Delivery process?

  • A. Sign-off completed Work Packages
  • B. Ensure the Business Case is kept under review
  • C. Report progress to the Project Board
  • D. Ensure that work on products is authorized and agreed with the team

Answer: D

NEW QUESTION 24

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  • A. Specify the desired result
  • B. Provide the resources and skills to deliver the desired result
  • C. Pay for the project
  • D. Specify the benefits of the project

Answer: B

NEW QUESTION 25

Which plan provides the Business Case with costs during the Initiating a Project process?

  • A. Initiation Stage Plan
  • B. Project Plan
  • C. Stage Plan
  • D. Team Plan

Answer: B

NEW QUESTION 26
......