Actualtests offers free demo for PRINCE2-Foundation exam. "PRINCE2 Foundation exam", also known as PRINCE2-Foundation exam, is a PRINCE2-Exams Certification. This set of posts, Passing the PRINCE2-Exams PRINCE2-Foundation exam, will help you answer those questions. The PRINCE2-Foundation Questions & Answers covers all the knowledge points of the real exam. 100% real PRINCE2-Exams PRINCE2-Foundation exams and revised by experts!
Free demo questions for PRINCE2-Exams PRINCE2-Foundation Exam Dumps Below:
NEW QUESTION 1
Which product records any project outcomes perceived as negative by stakeholders?
- A. Business Case
- B. Project Plan
- C. CommunicationManagement Strategy
- D. Project Product Description
Answer: A
NEW QUESTION 2
Which of the following is NOT a purpose of the Closing a Project process?
- A. Plan the activities required to close a project
- B. Enable a comparison of the original objectives of a project against what was actually achieved
- C. Enable premature closureif the Project Board request that a project should no longer continue
- D. Provide a fixed point at which acceptance for the project product is confirmed
Answer: A
NEW QUESTION 3
When considering risks, which describes an opportunity in a project?
- A. An uncertain event that couldhave a negative impact on objectives
- B. An uncertain event that could have a favourable impact on objectives
- C. An event that has occurred resulting in a negative impact on objectives
- D. An event that has occurred resulting in a favourable impact on objectives
Answer: B
NEW QUESTION 4
Which statement about the Directing a Project process is true?
- A. Provides a mechanism for the Project Board to assure that there is continuedbusiness justification
- B. Covers the day-to-day activities of the Project Manager
- C. Ensures there are regular progress meetings
- D. Begins on completion of the Initiating a Project process
Answer: A
NEW QUESTION 5
Which role is part of the project management team?
- A. Change Authority
- B. Quality assurance
- C. Stakeholder
- D. Corporate or programme management
Answer: A
NEW QUESTION 6
Which describes the 'Implement' step within the recommended risk management procedure?
- A. Project Support will allocate the risk budget to fund the selected risk responses
- B. The risk owner will decide the best response to control the risk
- C. The risk owner and the risk actionee will carry out activities to control and deal with the risk
- D. The Project Manager will formulate the RiskManagement Strategy
Answer: C
NEW QUESTION 7
Which is a purpose of a Lessons Log?
- A. Note any lessons that are raised in Checkpoint Reports
- B. Record that corrective action is being taken
- C. Escalate lessons to the Project Board
- D. Raise improvements with Project Assurance
Answer: A
NEW QUESTION 8
Why does PRINCE2 recommend three different levels of plans?
- A. To cover initiation, specialist work and exception situations
- B. To provide appropriate detailto each of the different levels of management within the project
- C. As an allowance for initiation, product delivery and project closure
- D. To match the different aspects of the product-based planning technique
Answer: B
NEW QUESTION 9
Which is a purpose of the Closing a Project process?
- A. Authorize the final stage of the project
- B. Confirm that all benefits defined in the Business Casehave been achieved
- C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
- D. Delegate day-to-day management of the end of the project to the Project Manager
Answer: C
NEW QUESTION 10
Which is a purpose of a Lessons Report?
- A. Improve the project management method for future projects
- B. Detail open issues and risks that need to be managed after the project has closed
- C. Compare the actual performance of the final stage against its plan
- D. Provide a summary of the benefits realized during the project
Answer: A
NEW QUESTION 11
Which is the purpose of the Change theme?
- A. Prevent change to baselined products
- B. Identify, assess and control any potential and approved changes to baselined products
- C. Establish mechanisms to monitor and compare actual achievements against those planned
- D. Assess and control uncertainty
Answer: B
NEW QUESTION 12
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
- A. Change
- B. Cross-functional
- C. Unique
- D. Risk
Answer: B
NEW QUESTION 13
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
- A. quality
- B. supplier
- C. risk
- D. product
Answer: B
NEW QUESTION 14
Which is a purpose of the Project Product Description?
- A. Define the key responsibilities for delivering product quality
- B. Provide information about the state of products
- C. Define the quality anticipated by the customer
- D. Provide product cost input tothe Business Case
Answer: C
NEW QUESTION 15
Which is NOT a true statement about the Managing a Stage Boundary process?
- A. It providessufficient information for the Project Board to review the success of the current stage
- B. It is used to create an Exception Plan if requested by the Project Board
- C. It provides a fixed point at which acceptance of the project product is confirmed
- D. It is executed at, or close to, the end of each management stage, except the final one
Answer: C
NEW QUESTION 16
Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
- A. Business Case
- B. Plans
- C. Progress
- D. Quality
Answer: C
NEW QUESTION 17
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
- A. a corporate
- B. a temporary
- C. an external
- D. a technical
Answer: B
NEW QUESTION 18
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
- A. Project Assurance
- B. Project Support
- C. the risk actionee
- D. the risk owner
Answer: C
NEW QUESTION 19
Which enables the project's products and all interdependencies to be clearly identified and documented?
- A. Product breakdown structure
- B. Quality Management Strategy
- C. Product-based planning technique
- D. Quality review technique
Answer: C
NEW QUESTION 20
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Progress
- B. Change
- C. Organization
- D. Quality
Answer: A
NEW QUESTION 21
In what process is the authorization to deliver the project's products given?
- A. Starting up a Project
- B. Initiating a Project
- C. Managing a Stage Boundary
- D. Directing a Project
Answer: D
NEW QUESTION 22
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
- A. Stage Plan
- B. Communication Management Strategy
- C. Follow-on action recommendations
- D. Quality Management Strategy
Answer: B
NEW QUESTION 23
Which is an objective of the Managing Product Delivery process?
- A. Sign-off completed Work Packages
- B. Ensure the Business Case is kept under review
- C. Report progress to the Project Board
- D. Ensure that work on products is authorized and agreed with the team
Answer: D
NEW QUESTION 24
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Specify the desired result
- B. Provide the resources and skills to deliver the desired result
- C. Pay for the project
- D. Specify the benefits of the project
Answer: B
NEW QUESTION 25
Which plan provides the Business Case with costs during the Initiating a Project process?
- A. Initiation Stage Plan
- B. Project Plan
- C. Stage Plan
- D. Team Plan
Answer: B