Exam Code: C2010-570 (Practice Exam Latest Test Questions VCE PDF)
Exam Name: IBM Maximo Asset Management V7.5 Implementation Exam
Certification Provider: IBM
Free Today! Guaranteed Training- Pass C2010-570 Exam.

2021 May C2010-570 Study Guide Questions:

Q31. When creating new Business Intelligence and Reporting Tool (BIRT) reports for use by the various IBM Maximo Asset Management applications, which step correctly describes a part of the process to add a new report? 

A. Before design files are imported, any associated library files must be imported 

B. Using the system configuration option, choose the report designer files to import 

C. Using the BIRT Report Designer Workstation, select the menu item to import the new report 

D. Before design files are imported, the location files that specify the location of the images and report files must be populated 

Answer: A 


Q32. Which fields must be specified to define an inventory item's reorder details? 

A. Reorder, Reorder Point, Safety Stock, and Order Unit 

B. Reorder, Reorder Point, Lead Time, and Primary Vendor 

C. Reorder, Reorder Point, Lead Time, and Economic Order Quantity 

D. Reorder, Reorder Point, Safety Stock, and Economic Order Quantity 

Answer: C 


Q33. What are two uses for the Assignment Manager application? (Choose two.) 

A. To dispatch labor and schedule work for an organization 

B. To create and manage work orders for assets and locations 

C. To report labor transactions by labor, by vendor/contract, by work order, or by ticket 

D. To specify which organizations and sites can use the information that is on the job plan and its tasks 

E. To view the requirements that were created from the work plan as well as the unplanned work on a work order 

Answer: A,E 


C2010-570 test preparation

Avant-garde C2010-570 book:

Q34. In the Receiving application, what are three standard values for the Inspection Status field? (Choose three.) 

A. APPR 

B. COMP 

C. WINSP 

D. CLOSE 

E. WAPPR 

F. WASSET 

Answer: B,C,F 


Q35. What are two uses for item classifications? (Choose two.) 

A. to group alternate items 

B. to search for alternate items 

C. to search for common items 

D. to search for items by specific attribute values 

E. to group common items under a single item number 

Answer: C,D 


Q36. ABC Corporation is about to deploy the IBM Maxi mo Asset Management V7.5 to manage the company assets. They want to add the GLACCOUNT attribute in the Assets application. 

Since the GLACCOUNT attribute already exists in the ASSET object, what is the best approach to meet this requirement? 

A. Customize the Asset JSP file and then rebuild and redeploy the maximo.ear file 

B. In the Application Designer, add the GLACCOUNT attribute in the Assets application using a control. 

C. In the Application Designer, duplicate the Conditional User Interface to show the GLACCOUNT attribute. 

D. In the Database Configuration application, configure the GLACCOUNT attribute properties; enable the Admin Mode, and Apply Configuration Changes. 

Answer: B 


C2010-570 latest exam

Free C2010-570 dump:

Q37. Which function is performed in the Quick Reporting application? 

A. Create failure code hierarchies 

B. Create job plans and safety plans 

C. Create preventive maintenance schedules 

D. Report actual labor, materials, and tools used in the work 

Answer: D 


Q38. What is a valid report option in the Labor Reporting application for external contractors or internal employees? 

A. Reporting labor by site 

B. Reporting labor by contract 

C. Reporting labor by work order 

D. Reporting labor by organization 

Answer: C 


Q39. Which method is used to view labor hours, costs, and material costs for a particular work order? 

A. from the Work Order Tracking application, select the Cost tab 

B. from the Work Order Tracking application, go to the Select Action menu and select View > Costs 

C. from the Actuals tab of Work Order Tracking application, download and summarize each of the table windows for Labor, Materials. Services, and Tools 

D. navigate to the Cost Management application, query for the work order in question to view estimated and actual hours and costs for labor in addition to estimated and actual costs for materials and service 

Answer: B 


Q40. A purchase order can be created from which three applications? (Choose three.) 

A. Assets 

B. Locations 

C. Contracts 

D. Item Master 

E. Purchase Requisitions 

F. Request for Quotations 

Answer: C,E,F