Cause all that matters here is passing the IBM C2010-555 exam. Cause all that you need is a high score of C2010-555 IBM Maximo Asset Management v7.6 Functional Analyst exam. The only one thing you need to do is downloading Ucertify C2010-555 exam study guides now. We will not let you down with our money-back guarantee.


♥♥ 2021 NEW RECOMMEND ♥♥

Free VCE & PDF File for IBM C2010-555 Real Exam (Full Version!)

★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW C2010-555 Exam Dumps (PDF & VCE):
Available on: http://www.surepassexam.com/C2010-555-exam-dumps.html

Q11. The maintenance supervisor is gathering data to use to build job plans. Only certain job plan will be carried over to the work orders based on the conditions applied

What data can have conditions?

A. Services, Tools, Assets

B. Labor, Tasks, Calendars

C. Labor, Services, Materials

D. Materials, Specifications, Tools

Answer: C


Q12. A company has acquired a contract for an asset covering labor, materials and tools. What must be created to capture this information?

A. A Master Contract

B. A Warranty Contract

C. A Purchase Contract

D. A Labor Rate Contract

Answer: A


Q13. Cutover work from cooling to healing is performed on the air handling units during the month of October each year. A requirement is to have the PM record generate Work Orders every Sunday during October

What settings are necessary?

A. Frequency = 1. Frequency Units = MONTHS, and Active Dates values entered on the Seasonal Dates tab.

B. Frequency = 7. Frequency Units = DAYS, and Active Days and Dates values entered on the Seasonal Dates tab.

C. Frequency = 7, Frequency Units= DAYS, and Generate Work Order When Meter Frequency is Reached checked.

D. Frequency = 1, Frequency Units = WEEKS, and Use Last Work Order's Start Date to Calculate Next Due Date checked.

Answer: A


Q14. A store manager needs to make changes to an asset via the Move/Modify action. Which of the following changes can be made"? (Choose two.)

A. Features

B. Storeroom

C. Asset's location

D. Class description

E. Parent/child relationship

Answer: C,D


Q15. A custom field has been added to the Work Order Tracking application to identify the inspector for environmental impacts of each work order. What type of role is used to assign the work order to the environmental inspector?

A. Person

B. Person Group

C. A set of data related to the record

D. A set of data related to the login user

Answer: A


Q16. A company has assets at multiple locations that require maintenance There is a requirement to have a single work order with charges rolled up to a single GL account.

How can that be achieved?

A. Create a task work order for each asset

B. Create a child work order for each asset

C. Add a job plan that has the assets associated

D. Add the assets in Multiple Assets, Locations and CIs

Answer: B


Q17. What is the reason to specify asset relationships?

A. To deploy assets.

B. To design the asset infrastructure.

C. To define a logical connection between separate assets.

D. To define how assets are allowed to behave when work is performed on them.

Answer: C


Q18. A company has a requirement that certain GL Accounts expire. In which application can this be defined?

A. Financial Periods

B. Cost Management

C. Chart of Accounts

D. Database Configuration

Answer: C


Q19. A company wishes to track items previously used for maintenance work on assets so they can easily be identified in the future. How can this be accomplished?

A. Non-Rotating Assets can be listed on the Spare Parts tab on the asset record.

B. Rotating items can be recorded on the Subassembly table on the asset record.

C. Non-Rotating items can be recorded on the Spare Parts tab on the asset record.

D. Consumable items can be recorded in the Spare Parts application against the asset record.

Answer: D


Q20. A company requires that laborers record the actual time they spent on a work order. The labor hours recorded are not automatically approved and the connection does not want the laborer to have access to the Work Order Tracking application.

Which application would the laborers use?

A. Invoicing

B. Time Sheets

C. Labor Reporting

D. Activities and Tasks

Answer: C