Proper study guides for Refresh GAQM Certified Lean Six Sigma Green Belt (CLSSGB) certified begins with GAQM CLSSGB preparation products which designed to deliver the 100% Guarantee CLSSGB questions by making you pass the CLSSGB test at your first time. Try the free CLSSGB demo right now.

Online GAQM CLSSGB free dumps demo Below:

NEW QUESTION 1
A Belt will occasionally do a quick experiment referred to as an OFAT which stands for __________ .

  • A. Only a Few Are Tested
  • B. Opposite Factors Affect Technique
  • C. One Factor At a Time
  • D. Ordinary Fractional Approach Technique

Answer: C

NEW QUESTION 2
Which element of waste best describes "the cost of an idle resource"?

  • A. Waiting
  • B. Motion
  • C. Inventory
  • D. Correction

Answer: A

NEW QUESTION 3
The Empirical Rule is important because it provides an estimate of the probability of an event occurring depending on the Standard Deviation from the Mean.

  • A. True
  • B. False

Answer: A

NEW QUESTION 4
After a Belt has put data through the smoothing process which chart would be used to look for trends in the data?

  • A. Moving Average Chart
  • B. Multi-Vari Chart
  • C. X bar Chart
  • D. Pareto Chart

Answer: A

NEW QUESTION 5
Which of the following is used to test the significance for the analysis of a Variance Table?

  • A. t Test
  • B. F Test
  • C. Chi Square Test
  • D. Acid Test

Answer: B

NEW QUESTION 6
Lean removes many forms of __________ so Six Sigma can focus on reducing __________.

  • A. Waste, variability
  • B. Inventory, defects
  • C. Waste, cost
  • D. Movement, variation

Answer: A

NEW QUESTION 7
Which of these is Discrete data?

  • A. Train arrived at 4:17 pm.
  • B. Race car consumed 23 gallons of fuel.
  • C. Of the 42 people on the bus, 12 went into the station.
  • D. It took 3 hours and 32 minutes to complete the marathon.

Answer: C

NEW QUESTION 8
It is a Type II error if we decide to reject the Null Hypothesis when it is actually true.

  • A. True
  • B. False

Answer: B

NEW QUESTION 9
When constructing a Fishbone Diagram using the __________ approach is the most classic arrangement.

  • A. 6M
  • B. 4M
  • C. 5M
  • D. Alphabetical

Answer: A

NEW QUESTION 10
Lean focuses on the sequence of activities and work required to produce a product or a service. This flow is called a __________.

  • A. Value-add Flow
  • B. Production Map
  • C. Value Stream
  • D. Operating Procedure

Answer: C

NEW QUESTION 11
The generation of a Regression Equation is justified when we __________. (Note: There are 4 correct answers).

  • A. Expect the relationship to be Linear between the output and inputs
  • B. Know that there is a non-linear relationship between output and input(s)
  • C. Need to understand how to control a process output by controlling the input(s)
  • D. Experience several process defects and have no other way to fix hem
  • E. When it is very expensive or too late to measure the output

Answer: ACDE

NEW QUESTION 12
Process Capability is a function of which of these?

  • A. Customer requirements
  • B. Process performance
  • C. Output over time
  • D. All of these answers are correct

Answer: D

NEW QUESTION 13
Skewed, or Mixed, Distributions occur when data comes from several sources that are supposed to be the same yet are not.

  • A. True
  • B. False

Answer: A

NEW QUESTION 14
The Six Sigma methodology had its origins at __________ in the late 1980’s when William Smith coined the name for quality related work being done there.

  • A. Motorola
  • B. Allied Signal
  • C. General Electric
  • D. Honeywell

Answer: A

NEW QUESTION 15
Lean had its origins in the development and practice of the __________ Production System.

  • A. Honda
  • B. Toyota
  • C. Ford
  • D. Motorola

Answer: B

NEW QUESTION 16
To create standardization of financial benefit calculations project savings are typically based on savings over what period of time?

  • A. 6 months
  • B. 12 months
  • C. 24 months
  • D. The remainder of the calendar year
  • E. The remainder of the fiscal year

Answer: B

NEW QUESTION 17
Lean focuses on the sequence of activities and work required to produce a product or a service. This flow is called a __________.

  • A. Value-add Flow
  • B. Production Map
  • C. Value Stream
  • D. Operating Procedure

Answer: C

NEW QUESTION 18
......

Recommend!! Get the Full CLSSGB dumps in VCE and PDF From Downloadfreepdf.net, Welcome to Download: https://www.downloadfreepdf.net/CLSSGB-pdf-download.html (New 200 Q&As Version)